Projects

Transit gas-main for Turkey, Greece, Macedonia and Yugoslavia. Sub-project: Compressor station “Provadia”

Client: "Glavbulgarstoroy" Jsc. - Town of Sofia

Completed: 2001 October

Erection of Sub-project Compressor station "Provadia" with 4 pcs. of new GTCA x 10 MW (Ten MW Gas turbine compressor aggregates for natural gas). Mechanical and technological mounting of technological equipment: compressor aggregates, coolers, inlet DN1200 and outlet DN1000 collector, technological pipelines and appliances for natural gas processing. Execution of CEW on parts: Chemical-technological, electrical, cabling, lighting and thunder protection automation of technological processes, Nondestructive tests of welding joints, anticorrosion coatings and heat insulation as a Subcontractor of "Glavbolgarstroy" JSC, town of Sofia. Client "Bulgargas" JSC, town of Sofia.